Key Takeaway
Clear Creek WS SCS Site 31 Dam is classified as significant hazard in Texas. It was completed in 1969 and is 57 years old. Its primary use is flood risk reduction. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 49 ft (taller than 93% in TX) |
| Dam Length | 1,300 ft |
| Dam Type | Earth |
| Max Storage | 956 acre-ft |
| Normal Storage | 68 acre-ft |
| Surface Area | 15 acres |
| Drainage Area | 2 sq mi |
| Max Discharge | 2 cfs |
| Year Completed | 1969 (57 years old) |
| NID ID | TX00710 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
CLEAR CREEK WATERSHED AUTHORITY;UPPER ELM RED SWCD
Local Government
Nearby Dams
Clear Creek WS SCS Site 32 Dam
Cooke, TX
Low Hazard 48 ftClear Creek WS SCS Site 30 Dam
Montague, TX
High Hazard 50 ftHudspeth Dam
Cooke, TX
Low Hazard 26 ftHl Settles Jr Dam
Montague, TX
Low Hazard 27 ftClear Creek WS SCS Site 28 Dam
Montague, TX
Low Hazard 46 ftClear Creek WS SCS Site 33 Dam
Cooke, TX
Low Hazard 59 ftClear Creek WS SCS Site 27a Dam
Montague, TX
Low Hazard 50 ftClear Creek WS SCS Site 29 Dam
Montague, TX
Low Hazard 59 ftFrequently Asked Questions
What is the hazard classification of Clear Creek WS SCS Site 31 Dam?
Clear Creek WS SCS Site 31 Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Clear Creek WS SCS Site 31 Dam?
Clear Creek WS SCS Site 31 Dam is owned by CLEAR CREEK WATERSHED AUTHORITY;UPPER ELM RED SWCD (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Clear Creek WS SCS Site 31 Dam built?
Clear Creek WS SCS Site 31 Dam was completed in 1969, making it 57 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Clear Creek WS SCS Site 31 Dam?
Clear Creek WS SCS Site 31 Dam serves the following purposes: Flood Risk Reduction, Fire Protection, Stock, Or Small Fish Pond, Debris Control. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Clear Creek WS SCS Site 31 Dam?
Clear Creek WS SCS Site 31 Dam has a dam height of 49 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Clear Creek WS SCS Site 31 Dam last inspected?
Clear Creek WS SCS Site 31 Dam was last inspected on March 7, 2017. Inspection dates indicate when a formal review occurred, not the results of that inspection.