York Creek WS SCS Site 13 Dam
Key Takeaway
York Creek WS SCS Site 13 Dam is classified as high hazard in Texas. It was completed in 1964 and is 62 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 34 ft (taller than 76% in TX) |
| Dam Length | 2,360 ft |
| Dam Type | Earth |
| Max Storage | 5.0K acre-ft |
| Normal Storage | 652 acre-ft |
| Surface Area | 126 acres |
| Drainage Area | 10 sq mi |
| Max Discharge | 30,232 cfs |
| Year Completed | 1964 (62 years old) |
| NID ID | TX01611 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
COMAL-GUADALUPE SWCD;YORK CREEK IMPROVEMENT DISTRICT
Local Government
Nearby Dams
Cottonwood Creek Detention Dam
Hays, TX
Low Hazard 13 ftScrutchin Lake Dam
Hays, TX
Low Hazard 30 ftJohn F Baugh Dam
Hays, TX
Low Hazard 15 ftWebster Lake Dam
Hays, TX
Low Hazard 20 ftYork Creek WS SCS Site 14 Dam
Guadalupe, TX
High Hazard 25 ftCummings Dam
Hays, TX
Significant Hazard 10 ftSan Marcos State Fish Hatchery
Hays, TX
Significant Hazard 21 ftYork Creek WS SCS Site 15 Dam
Guadalupe, TX
Low Hazard 36 ftFrequently Asked Questions
What is the hazard classification of York Creek WS SCS Site 13 Dam?
York Creek WS SCS Site 13 Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates York Creek WS SCS Site 13 Dam?
York Creek WS SCS Site 13 Dam is owned by COMAL-GUADALUPE SWCD;YORK CREEK IMPROVEMENT DISTRICT (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was York Creek WS SCS Site 13 Dam built?
York Creek WS SCS Site 13 Dam was completed in 1964, making it 62 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of York Creek WS SCS Site 13 Dam?
York Creek WS SCS Site 13 Dam serves the following purposes: Flood Risk Reduction, Fire Protection, Stock, Or Small Fish Pond, Recreation, Debris Control. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is York Creek WS SCS Site 13 Dam?
York Creek WS SCS Site 13 Dam has a dam height of 34 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was York Creek WS SCS Site 13 Dam last inspected?
York Creek WS SCS Site 13 Dam was last inspected on May 23, 2023. Inspection dates indicate when a formal review occurred, not the results of that inspection.