Wiles Pond Dam
Key Takeaway
Wiles Pond Dam is classified as high hazard in South Carolina. Its primary use is recreation. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 25 ft (taller than 62.5% in SC) |
| Max Storage | 140 acre-ft |
| Normal Storage | 104 acre-ft |
| Surface Area | 13 acres |
| NID ID | SC02461 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
JULIAN D WILES TRUST
Private
Nearby Dams
Reid House Pond Dam
Calhoun, SC
Low Hazard 23 ftGaynen Pond Dam
Calhoun, SC
Unknown 19 ftGadden Pond Dam
Calhoun, SC
Unknown 23 ftWay Pond Dam
Calhoun, SC
Unknown 19 ftHane Little Pond Dam
Calhoun, SC
Low Hazard 22 ftHane Big Pond Dam
Calhoun, SC
Low Hazard 24 ftShehane Cabin Dam
Calhoun, SC
Low Hazard 26 ftWk Chastain Pond Dam
Calhoun, SC
Low Hazard 16 ftFrequently Asked Questions
What is the hazard classification of Wiles Pond Dam?
Wiles Pond Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Wiles Pond Dam?
Wiles Pond Dam is owned by JULIAN D WILES TRUST (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
What is the primary purpose of Wiles Pond Dam?
Wiles Pond Dam serves the following purposes: Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Wiles Pond Dam?
Wiles Pond Dam has a dam height of 25 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Wiles Pond Dam last inspected?
Wiles Pond Dam was last inspected on October 5, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.