Waterbury Roadway Embankment
Key Takeaway
Waterbury Roadway Embankment is classified as high hazard in New York. It was completed in 1914 and is 112 years old. Its primary use is hydroelectric. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 5 ft (taller than 0.1% in NY) |
| Dam Length | 400 ft |
| Dam Type | Earth |
| Max Storage | 66.5K acre-ft |
| Normal Storage | 66.5K acre-ft |
| Surface Area | 3,500 acres |
| Drainage Area | 191 sq mi |
| Max Discharge | 0 cfs |
| Year Completed | 1914 (112 years old) |
| NID ID | NY00377 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Not Listed
Nearby Dams
Bennetts Bridge - Dike C
Oswego, NY
High Hazard 10 ftBennetts Bridge - Dike B
Oswego, NY
High Hazard 13 ftSage Pond Dam
Oswego, NY
Significant Hazard 13 ftBennetts Bridge
Oswego, NY
High Hazard 35 ftKasoag Lake Dam
Oswego, NY
Low Hazard 10 ftCedar Lake Dam
Oswego, NY
Significant Hazard 15 ftOneida #7 Pond #1 Dam & Dike
Oneida, NY
Low Hazard 11 ftAutumn Lake Dam
Oswego, NY
Low Hazard 28 ftFrequently Asked Questions
What is the hazard classification of Waterbury Roadway Embankment?
Waterbury Roadway Embankment is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Waterbury Roadway Embankment?
Waterbury Roadway Embankment is owned by information not available (Not Listed). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Waterbury Roadway Embankment built?
Waterbury Roadway Embankment was completed in 1914, making it 112 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Waterbury Roadway Embankment?
Waterbury Roadway Embankment serves the following purposes: Hydroelectric, Recreation, Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Waterbury Roadway Embankment?
Waterbury Roadway Embankment has a dam height of 5 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Waterbury Roadway Embankment last inspected?
Waterbury Roadway Embankment was last inspected on August 30, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.