Key Takeaway
Upper Washita River WS SCS Site 26 Dam is classified as significant hazard in Texas. It was completed in 1963 and is 63 years old. Its primary use is flood risk reduction. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 33 ft (taller than 74.3% in TX) |
| Dam Length | 1,185 ft |
| Dam Type | Earth |
| Max Storage | 911 acre-ft |
| Normal Storage | 174 acre-ft |
| Surface Area | 25 acres |
| Drainage Area | 4 sq mi |
| Max Discharge | 973 cfs |
| Year Completed | 1963 (63 years old) |
| NID ID | TX02496 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
HEMPHILL COUNTY;HEMPHILL COUNTY SWCD
Local Government
Nearby Dams
Lake June Dam
Hemphill, TX
Low Hazard 16 ftUpper Washita River WS SCS Site 28 Dam
Hemphill, TX
Low Hazard 27 ftUpper Washita River WS SCS Site 27 Dam
Hemphill, TX
Low Hazard 32 ftYoung Brothers Gss
Hemphill, TX
Low Hazard 19 ftUpper Washita River WS SCS Site 25 Dam
Hemphill, TX
Low Hazard 31 ftUpper Washita River WS SCS Site 15a Dam
Hemphill, TX
Low Hazard 30 ftUpper Washita River WS SCS Site 15 Dam
Hemphill, TX
Low Hazard 35 ftUpper Washita River WS SCS Site 29 Dam
Hemphill, TX
Low Hazard 26 ftFrequently Asked Questions
What is the hazard classification of Upper Washita River WS SCS Site 26 Dam?
Upper Washita River WS SCS Site 26 Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Upper Washita River WS SCS Site 26 Dam?
Upper Washita River WS SCS Site 26 Dam is owned by HEMPHILL COUNTY;HEMPHILL COUNTY SWCD (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Upper Washita River WS SCS Site 26 Dam built?
Upper Washita River WS SCS Site 26 Dam was completed in 1963, making it 63 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Upper Washita River WS SCS Site 26 Dam?
Upper Washita River WS SCS Site 26 Dam serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Upper Washita River WS SCS Site 26 Dam?
Upper Washita River WS SCS Site 26 Dam has a dam height of 33 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Upper Washita River WS SCS Site 26 Dam last inspected?
Upper Washita River WS SCS Site 26 Dam was last inspected on December 18, 2019. Inspection dates indicate when a formal review occurred, not the results of that inspection.