Upper Mount Olivet

CLEAR CREEK-TR· Jefferson, Colorado· Built 1966· Earth· 12 ft tall
Low Hazard Irrigation Private

Key Takeaway

Upper Mount Olivet is classified as low hazard in Colorado. It was completed in 1966 and is 60 years old. Its primary use is irrigation.

Physical Details

Dam Height 12 ft (taller than 11% in CO)
Dam Length2,342 ft
Dam TypeEarth
Max Storage104 acre-ft
Normal Storage71 acre-ft
Surface Area12 acres
Drainage Area0 sq mi
Max Discharge220 cfs
Year Completed1966 (60 years old)
NID IDCO00202

Safety Information

Low Hazard

No probable loss of human life and low economic/environmental losses expected.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: May 11, 1995
State Regulated: Yes
Regulatory Agency: DWR

Ownership

MT. OLIVET CEMETERY ASSOC. (BOB NELSON)

Private

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Upper Mount Olivet?

Upper Mount Olivet is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Upper Mount Olivet?

Upper Mount Olivet is owned by MT. OLIVET CEMETERY ASSOC. (BOB NELSON) (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Upper Mount Olivet built?

Upper Mount Olivet was completed in 1966, making it 60 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Upper Mount Olivet?

Upper Mount Olivet serves the following purposes: Irrigation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Upper Mount Olivet?

Upper Mount Olivet has a dam height of 12 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Upper Mount Olivet last inspected?

Upper Mount Olivet was last inspected on May 11, 1995. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.