Upper Bosque River WS SCS Site 28 Dam is classified as low hazard in Texas. It was completed in 1970 and is 56 years old. Its primary use is flood risk reduction.
Physical Details
| Dam Height | 49 ft (taller than 93% in TX) |
| Dam Length | 1,900 ft |
| Dam Type | Earth |
| Max Storage | 2.3K acre-ft |
| Normal Storage | 117 acre-ft |
| Surface Area | 18 acres |
| Drainage Area | 6 sq mi |
| Year Completed | 1970 (56 years old) |
| NID ID | TX00789 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
HAMILTON COUNTY;HAMILTON-CORYELL SWCD 506
Local Government
Nearby Dams
Upper Bosque River WS SCS Site 27 Dam
Erath, TX
High Hazard 70 ftUpper Bosque River WS SCS Site 25 Dam
Erath, TX
High Hazard 57 ftUpper Bosque River WS SCS Site 26 Dam
Erath, TX
High Hazard 47 ftUpper Bosque River WS SCS Site 24 Dam
Erath, TX
Significant Hazard 50 ftLake Bedrock Dam
Erath, TX
Low Hazard 20 ftAc Mcmillian Dam
Hamilton, TX
Low Hazard 19 ftGreen Creek WS SCS Site 13 Dam
Erath, TX
Low Hazard 41 ftFillingim Lake Dam
Hamilton, TX
Low Hazard 32 ftFrequently Asked Questions
What is the hazard classification of Upper Bosque River WS SCS Site 28 Dam?
Upper Bosque River WS SCS Site 28 Dam is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Upper Bosque River WS SCS Site 28 Dam?
Upper Bosque River WS SCS Site 28 Dam is owned by HAMILTON COUNTY;HAMILTON-CORYELL SWCD 506 (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Upper Bosque River WS SCS Site 28 Dam built?
Upper Bosque River WS SCS Site 28 Dam was completed in 1970, making it 56 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Upper Bosque River WS SCS Site 28 Dam?
Upper Bosque River WS SCS Site 28 Dam serves the following purposes: Flood Risk Reduction, Fire Protection, Stock, Or Small Fish Pond, Irrigation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Upper Bosque River WS SCS Site 28 Dam?
Upper Bosque River WS SCS Site 28 Dam has a dam height of 49 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Upper Bosque River WS SCS Site 28 Dam last inspected?
Upper Bosque River WS SCS Site 28 Dam was last inspected on April 6, 1972. Inspection dates indicate when a formal review occurred, not the results of that inspection.