Thompson Pond Dam

TR-EZELL BRANCH· Spartanburg, South Carolina· Built 1959· 28 ft tall
High Hazard Recreation Private

Key Takeaway

Thompson Pond Dam is classified as high hazard in South Carolina. It was completed in 1959 and is 67 years old. Its primary use is recreation. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.

Physical Details

Dam Height 28 ft (taller than 74.2% in SC)
Max Storage75 acre-ft
Normal Storage62 acre-ft
Surface Area7 acres
Year Completed1959 (67 years old)
NID IDSC02247

Safety Information

High Hazard

Loss of human life is likely if the dam fails.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: Yes
Last Inspection: September 27, 2021
State Regulated: Yes
Regulatory Agency: SC DHEC

Ownership

PHYLLIS JONES;RANDALL L PRICE AND DARLENE G PRICE

Private

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Thompson Pond Dam?

Thompson Pond Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Thompson Pond Dam?

Thompson Pond Dam is owned by PHYLLIS JONES;RANDALL L PRICE AND DARLENE G PRICE (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Thompson Pond Dam built?

Thompson Pond Dam was completed in 1959, making it 67 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Thompson Pond Dam?

Thompson Pond Dam serves the following purposes: Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Thompson Pond Dam?

Thompson Pond Dam has a dam height of 28 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Thompson Pond Dam last inspected?

Thompson Pond Dam was last inspected on September 27, 2021. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.