Tamu Detention Dam No 8

UNNAMED TRIBUTARY OF WOLF PEN CREEK· Brazos, Texas· Built 2002· Earth· 8 ft tall
Significant Hazard State Government

Key Takeaway

Tamu Detention Dam No 8 is classified as significant hazard in Texas. It was completed in 2002 and is 24 years old. Significant hazard means failure could cause economic or environmental damage. Learn more.

Physical Details

Dam Height 8 ft (taller than 1.1% in TX)
Dam Length2,037 ft
Dam TypeEarth
Max Storage101 acre-ft
Normal Storage0 acre-ft
Surface Area20 acres
Drainage Area1 sq mi
Max Discharge1,806 cfs
Year Completed2002 (24 years old)
NID IDTX07355

Safety Information

Significant Hazard

No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: Yes
Last Inspection: September 27, 2021
State Regulated: Yes
Regulatory Agency: TCEQ

Ownership

THE TEXAS A&M UNIVERSITY SYSTEM

State Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Tamu Detention Dam No 8?

Tamu Detention Dam No 8 is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Tamu Detention Dam No 8?

Tamu Detention Dam No 8 is owned by THE TEXAS A&M UNIVERSITY SYSTEM (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Tamu Detention Dam No 8 built?

Tamu Detention Dam No 8 was completed in 2002, making it 24 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

How tall is Tamu Detention Dam No 8?

Tamu Detention Dam No 8 has a dam height of 8 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Tamu Detention Dam No 8 last inspected?

Tamu Detention Dam No 8 was last inspected on September 27, 2021. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.