Key Takeaway
Sweetwater Creek #16 is classified as significant hazard in Tennessee. It was completed in 1978 and is 48 years old. Its primary use is flood risk reduction. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Length | 438 ft |
| Dam Type | Earth |
| Max Storage | 215 acre-ft |
| Normal Storage | 44 acre-ft |
| Surface Area | 5 acres |
| Drainage Area | 1 sq mi |
| Year Completed | 1978 (48 years old) |
| NID ID | TN10707 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
SWEETWATER CREEK W.D.
Local Government
Nearby Dams
Frequently Asked Questions
What is the hazard classification of Sweetwater Creek #16?
Sweetwater Creek #16 is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Sweetwater Creek #16?
Sweetwater Creek #16 is owned by SWEETWATER CREEK W.D. (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Sweetwater Creek #16 built?
Sweetwater Creek #16 was completed in 1978, making it 48 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Sweetwater Creek #16?
Sweetwater Creek #16 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Sweetwater Creek #16 last inspected?
Sweetwater Creek #16 was last inspected on June 16, 2020. Inspection dates indicate when a formal review occurred, not the results of that inspection.