Surmeier

LITTLE WHITLEY GULCH CREEK SNAKE RIVER· Payette, Idaho· Built 1978· 32 ft tall
Significant Hazard Other Private

Key Takeaway

Surmeier is classified as significant hazard in Idaho. It was completed in 1978 and is 48 years old. Its primary use is other. Significant hazard means failure could cause economic or environmental damage. Learn more.

Physical Details

Dam Height 32 ft (taller than 59.6% in ID)
Dam Length215 ft
Normal Storage26 acre-ft
Surface Area3 acres
Drainage Area0 sq mi
Max Discharge35 cfs
Year Completed1978 (48 years old)
NID IDID00130

Safety Information

Significant Hazard

No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: June 11, 2019
State Regulated: Yes
Regulatory Agency: IDWR

Ownership

Private

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Surmeier?

Surmeier is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Surmeier?

Surmeier is owned by information not available (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Surmeier built?

Surmeier was completed in 1978, making it 48 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Surmeier?

Surmeier serves the following purposes: Other. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Surmeier?

Surmeier has a dam height of 32 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Surmeier last inspected?

Surmeier was last inspected on June 11, 2019. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.