Spring Run #2

SPRING RUN· El Paso, Colorado· Built 1970· Earth· 39 ft tall
High Hazard Irrigation Flood Risk Reduction Private

Key Takeaway

Spring Run #2 is classified as high hazard in Colorado. It was completed in 1970 and is 56 years old. Its primary use is irrigation. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.

Physical Details

Dam Height 39 ft (taller than 80.5% in CO)
Dam Length710 ft
Dam TypeEarth
Max Storage511 acre-ft
Normal Storage311 acre-ft
Surface Area20 acres
Drainage Area2 sq mi
Max Discharge11,745 cfs
Year Completed1970 (56 years old)
NID IDCO00404

Safety Information

High Hazard

Loss of human life is likely if the dam fails.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: Yes
Last Inspection: March 24, 2022
State Regulated: Yes
Regulatory Agency: DWR

Ownership

MYRON STRATTON HOME

Private

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Spring Run #2?

Spring Run #2 is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Spring Run #2?

Spring Run #2 is owned by MYRON STRATTON HOME (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Spring Run #2 built?

Spring Run #2 was completed in 1970, making it 56 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Spring Run #2?

Spring Run #2 serves the following purposes: Irrigation, Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Spring Run #2?

Spring Run #2 has a dam height of 39 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Spring Run #2 last inspected?

Spring Run #2 was last inspected on March 24, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.