Key Takeaway
Sheer Bliss is classified as significant hazard in Colorado. It was completed in 2007 and is 19 years old. Its primary use is water supply. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 22 ft (taller than 43.8% in CO) |
| Dam Length | 180 ft |
| Dam Type | Earth |
| Max Storage | 13 acre-ft |
| Normal Storage | 11 acre-ft |
| Surface Area | 1 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 70 cfs |
| Year Completed | 2007 (19 years old) |
| Year Modified | 2016 |
| NID ID | CO03006 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
ASPEN SKIING COMPANY (PASSERINI, RAUL)
Private
Nearby Dams
Lake Deborah
Pitkin, CO
High Hazard 28 ftWildcat
Pitkin, CO
High Hazard 75 ftChristenson
Pitkin, CO
Significant Hazard 17 ftLazy O Reservoir No 2
Pitkin, CO
Significant Hazard 18 ftLeonard Thomas Reservoir
Pitkin, CO
Significant Hazard 19 ftSaddle Pond
Pitkin, CO
High Hazard 27 ftZiff Dam
Pitkin, CO
Low Hazard 23 ftValana K Reservoir No. 1
Pitkin, CO
Significant Hazard 19 ftFrequently Asked Questions
What is the hazard classification of Sheer Bliss?
Sheer Bliss is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Sheer Bliss?
Sheer Bliss is owned by ASPEN SKIING COMPANY (PASSERINI, RAUL) (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Sheer Bliss built?
Sheer Bliss was completed in 2007, making it 19 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Sheer Bliss?
Sheer Bliss serves the following purposes: Water Supply. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Sheer Bliss?
Sheer Bliss has a dam height of 22 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Sheer Bliss last inspected?
Sheer Bliss was last inspected on September 28, 2021. Inspection dates indicate when a formal review occurred, not the results of that inspection.