Seco Creek Recharge Dam

SECO CREEK· Medina, Texas· Built 1983· Earth· 14 ft tall
Low Hazard Other Local Government

Key Takeaway

Seco Creek Recharge Dam is classified as low hazard in Texas. It was completed in 1983 and is 43 years old. Its primary use is other.

Physical Details

Dam Height 14 ft (taller than 12.5% in TX)
Dam Length280 ft
Dam TypeEarth
Max Storage50 acre-ft
Normal Storage2 acre-ft
Surface Area2 acres
Drainage Area61 sq mi
Max Discharge54,000 cfs
Year Completed1983 (43 years old)
NID IDTX05828

Safety Information

Low Hazard

No probable loss of human life and low economic/environmental losses expected.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: April 1, 2004
State Regulated: Yes
Regulatory Agency: TCEQ

Ownership

EDWARDS AQUIFER AUTHORITY

Local Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Seco Creek Recharge Dam?

Seco Creek Recharge Dam is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Seco Creek Recharge Dam?

Seco Creek Recharge Dam is owned by EDWARDS AQUIFER AUTHORITY (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Seco Creek Recharge Dam built?

Seco Creek Recharge Dam was completed in 1983, making it 43 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Seco Creek Recharge Dam?

Seco Creek Recharge Dam serves the following purposes: Other. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Seco Creek Recharge Dam?

Seco Creek Recharge Dam has a dam height of 14 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Seco Creek Recharge Dam last inspected?

Seco Creek Recharge Dam was last inspected on April 1, 2004. Inspection dates indicate when a formal review occurred, not the results of that inspection.