SCS-Upper Black Bear Creek Site-75
Key Takeaway
SCS-Upper Black Bear Creek Site-75 is classified as high hazard in Oklahoma. It was completed in 1969 and is 57 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 25 ft (taller than 29.9% in OK) |
| Dam Length | 1,780 ft |
| Dam Type | Earth |
| Max Storage | 363 acre-ft |
| Normal Storage | 65 acre-ft |
| Surface Area | 14 acres |
| Max Discharge | 675 cfs |
| Year Completed | 1969 (57 years old) |
| NID ID | OK01436 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
NOBLE CO CONS DIST
State Government
Nearby Dams
SCS-Upper Black Bear Creek Site-76
Noble, OK
High Hazard 31 ftSCS-Upper Black Bear Creek Site-74
Noble, OK
Significant Hazard 36 ftSCS-Upper Black Bear Creek Site-73
Noble, OK
Significant Hazard 36 ftSCS-Upper Black Bear Creek Site-06
Noble, OK
Low Hazard 32 ftSCS-Upper Black Bear Creek Site-07
Noble, OK
Low Hazard 24 ftSCS-Long Branch Creek Site-05a
Noble, OK
Low Hazard 16 ftSCS-Upper Black Bear Creek Site-72
Noble, OK
Low Hazard 44 ftSCS-Long Branch Creek Site-04
Noble, OK
Low Hazard 21 ftFrequently Asked Questions
What is the hazard classification of SCS-Upper Black Bear Creek Site-75?
SCS-Upper Black Bear Creek Site-75 is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates SCS-Upper Black Bear Creek Site-75?
SCS-Upper Black Bear Creek Site-75 is owned by NOBLE CO CONS DIST (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was SCS-Upper Black Bear Creek Site-75 built?
SCS-Upper Black Bear Creek Site-75 was completed in 1969, making it 57 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of SCS-Upper Black Bear Creek Site-75?
SCS-Upper Black Bear Creek Site-75 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is SCS-Upper Black Bear Creek Site-75?
SCS-Upper Black Bear Creek Site-75 has a dam height of 25 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was SCS-Upper Black Bear Creek Site-75 last inspected?
SCS-Upper Black Bear Creek Site-75 was last inspected on July 7, 2011. Inspection dates indicate when a formal review occurred, not the results of that inspection.