SCS-Roaring Creek Site-105
Key Takeaway
SCS-Roaring Creek Site-105 is classified as low hazard in Oklahoma. It was completed in 1963 and is 63 years old. Its primary use is flood risk reduction.
Physical Details
| Dam Height | 30 ft (taller than 54.9% in OK) |
| Dam Length | 1,000 ft |
| Dam Type | Earth |
| Max Storage | 67 acre-ft |
| Normal Storage | 24 acre-ft |
| Surface Area | 5 acres |
| Max Discharge | 730 cfs |
| Year Completed | 1963 (63 years old) |
| NID ID | OK00201 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
GRADY CO CONS DIST
State Government
Nearby Dams
SCS-Roaring Creek Site-001
Grady, OK
Low Hazard 34 ftSCS-Roaring Creek Site-015
Grady, OK
Low Hazard 25 ftSCS-Roaring Creek Site-B1
Grady, OK
High Hazard 39 ftSCS-Roaring Creek Site-002
Grady, OK
Low Hazard 33 ftSCS-Roaring Creek Site-101
Grady, OK
Low Hazard 19 ftSCS-Round Creek Site-9
Grady, OK
Low Hazard 25 ftSCS-Roaring Creek Site-106
Grady, OK
Significant Hazard 19 ftSCS-Winter Creek Site-11
Grady, OK
Low Hazard 29 ftFrequently Asked Questions
What is the hazard classification of SCS-Roaring Creek Site-105?
SCS-Roaring Creek Site-105 is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates SCS-Roaring Creek Site-105?
SCS-Roaring Creek Site-105 is owned by GRADY CO CONS DIST (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was SCS-Roaring Creek Site-105 built?
SCS-Roaring Creek Site-105 was completed in 1963, making it 63 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of SCS-Roaring Creek Site-105?
SCS-Roaring Creek Site-105 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is SCS-Roaring Creek Site-105?
SCS-Roaring Creek Site-105 has a dam height of 30 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was SCS-Roaring Creek Site-105 last inspected?
SCS-Roaring Creek Site-105 was last inspected on January 1, 1980. Inspection dates indicate when a formal review occurred, not the results of that inspection.