SCS-Otter Creek Site-5
Key Takeaway
SCS-Otter Creek Site-5 is classified as significant hazard in Oklahoma. It was completed in 1973 and is 53 years old. Its primary use is flood risk reduction. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 30 ft (taller than 54.9% in OK) |
| Dam Length | 1,930 ft |
| Dam Type | Earth |
| Max Storage | 493 acre-ft |
| Normal Storage | 47 acre-ft |
| Surface Area | 15 acres |
| Max Discharge | 1,380 cfs |
| Year Completed | 1973 (53 years old) |
| NID ID | OK20673 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
KIOWA CO CONS DIST
State Government
Nearby Dams
SCS-Otter Creek Site-4
Kiowa, OK
High Hazard 41 ftSCS-Otter Creek Site-6
Kiowa, OK
Low Hazard 26 ftSCS-Otter Creek Site-3
Kiowa, OK
High Hazard 45 ftOknoname 075009
Kiowa, OK
Low Hazard 15 ftCooperton Dam
Comanche, OK
Low Hazard 25 ftGrama Dam
Comanche, OK
High Hazard 43 ftComanche Dam
Comanche, OK
High Hazard 39 ftCaddo Dam
Comanche, OK
Low Hazard 28 ftFrequently Asked Questions
What is the hazard classification of SCS-Otter Creek Site-5?
SCS-Otter Creek Site-5 is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates SCS-Otter Creek Site-5?
SCS-Otter Creek Site-5 is owned by KIOWA CO CONS DIST (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was SCS-Otter Creek Site-5 built?
SCS-Otter Creek Site-5 was completed in 1973, making it 53 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of SCS-Otter Creek Site-5?
SCS-Otter Creek Site-5 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is SCS-Otter Creek Site-5?
SCS-Otter Creek Site-5 has a dam height of 30 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was SCS-Otter Creek Site-5 last inspected?
SCS-Otter Creek Site-5 was last inspected on September 12, 2011. Inspection dates indicate when a formal review occurred, not the results of that inspection.