SCS-Brushy Peaceable Creek Site-008
Key Takeaway
SCS-Brushy Peaceable Creek Site-008 is classified as low hazard in Oklahoma. It was completed in 1999 and is 27 years old. Its primary use is flood risk reduction.
Physical Details
| Dam Height | 27 ft (taller than 43% in OK) |
| Dam Length | 1,275 ft |
| Dam Type | Earth |
| Max Storage | 291 acre-ft |
| Normal Storage | 42 acre-ft |
| Drainage Area | 1 sq mi |
| Year Completed | 1999 (27 years old) |
| NID ID | OK22278 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
PITTSBURG CO. CONSV. DIST
State Government
Nearby Dams
Oknoname 121006
Pittsburg, OK
Low Hazard 16 ftSCS-Brushy Peaceable Creek Site-009
Pittsburg, OK
Low Hazard 25 ftSCS-Brushy Peaceable Creek Site-010
Pittsburg, OK
Low Hazard 33 ftSCS-Brushy Peaceable Creek Site-004
Pittsburg, OK
Low Hazard 32 ftSCS-Brushy Peaceable Creek Site-011
Pittsburg, OK
Low Hazard 33 ftOknoname 30135
Pittsburg, OK
Low Hazard 21 ftSCS-Brushy Peaceable Creek Site-026
Pittsburg, OK
Significant Hazard 38 ftSCS-Brushy Peaceable Creek Site-003
Pittsburg, OK
Low Hazard 25 ftFrequently Asked Questions
What is the hazard classification of SCS-Brushy Peaceable Creek Site-008?
SCS-Brushy Peaceable Creek Site-008 is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates SCS-Brushy Peaceable Creek Site-008?
SCS-Brushy Peaceable Creek Site-008 is owned by PITTSBURG CO. CONSV. DIST (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was SCS-Brushy Peaceable Creek Site-008 built?
SCS-Brushy Peaceable Creek Site-008 was completed in 1999, making it 27 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of SCS-Brushy Peaceable Creek Site-008?
SCS-Brushy Peaceable Creek Site-008 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is SCS-Brushy Peaceable Creek Site-008?
SCS-Brushy Peaceable Creek Site-008 has a dam height of 27 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was SCS-Brushy Peaceable Creek Site-008 last inspected?
SCS-Brushy Peaceable Creek Site-008 was last inspected on December 31, 2011. Inspection dates indicate when a formal review occurred, not the results of that inspection.