SCS-Big Wewoka Creek Site-02 is classified as low hazard in Oklahoma. It was completed in 1957 and is 69 years old. Its primary use is flood risk reduction.
Physical Details
| Dam Height | 24 ft (taller than 26.9% in OK) |
| Dam Length | 800 ft |
| Dam Type | Earth |
| Max Storage | 327 acre-ft |
| Normal Storage | 83 acre-ft |
| Surface Area | 18 acres |
| Max Discharge | 2,400 cfs |
| Year Completed | 1957 (69 years old) |
| NID ID | OK01300 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
SEMINOLE CO CONS DIST
State Government
Nearby Dams
SCS-Big Wewoka Creek Site-01
Seminole, OK
Low Hazard 17 ftSCS-Big Wewoka Creek Site-03
Seminole, OK
Low Hazard 24 ftSCS-Big Wewoka Creek Site-04
Seminole, OK
Low Hazard 35 ftOknoname 133002
Seminole, OK
Low Hazard 18 ftOknoname 30208
Pottawatomie, OK
Low Hazard 15 ftSCS-Big Wewoka Creek Site-06
Seminole, OK
Low Hazard 22 ftSCS-Big Wewoka Creek Site-05
Seminole, OK
Low Hazard 28 ftOknoname 125016
Pottawatomie, OK
Unknown 18 ftFrequently Asked Questions
What is the hazard classification of SCS-Big Wewoka Creek Site-02?
SCS-Big Wewoka Creek Site-02 is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates SCS-Big Wewoka Creek Site-02?
SCS-Big Wewoka Creek Site-02 is owned by SEMINOLE CO CONS DIST (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was SCS-Big Wewoka Creek Site-02 built?
SCS-Big Wewoka Creek Site-02 was completed in 1957, making it 69 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of SCS-Big Wewoka Creek Site-02?
SCS-Big Wewoka Creek Site-02 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is SCS-Big Wewoka Creek Site-02?
SCS-Big Wewoka Creek Site-02 has a dam height of 24 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was SCS-Big Wewoka Creek Site-02 last inspected?
SCS-Big Wewoka Creek Site-02 was last inspected on January 1, 1980. Inspection dates indicate when a formal review occurred, not the results of that inspection.