Robert Connelly Dam 3
Key Takeaway
Robert Connelly Dam 3 is classified as low hazard in South Carolina. Its primary use is irrigation.
Physical Details
| Dam Height | 14 ft (taller than 19.3% in SC) |
| Max Storage | 105 acre-ft |
| Normal Storage | 63 acre-ft |
| Surface Area | 10 acres |
| NID ID | SC02656 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
ELMA CONNELLY ET AL TRUSTEES
Private
Nearby Dams
Robert Connelly Dam 2
Allendale, SC
High Hazard 20 ftW B Manuel Dam
Allendale, SC
High Hazard 15 ftMathias Pond Dam
Allendale, SC
Low Hazard 17 ftSpigeners Pond Dam
Allendale, SC
Low Hazard 25 ftSanders Pond Dam
Allendale, SC
Low Hazard 8 ftBob and Dorothy Sanders Dam
Barnwell, SC
Low Hazard 17 ftBarkers Pond Dam
Allendale, SC
High Hazard 18 ftAllendale Waste Pond Dam
Allendale, SC
Unknown 11 ftFrequently Asked Questions
What is the hazard classification of Robert Connelly Dam 3?
Robert Connelly Dam 3 is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Robert Connelly Dam 3?
Robert Connelly Dam 3 is owned by ELMA CONNELLY ET AL TRUSTEES (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
What is the primary purpose of Robert Connelly Dam 3?
Robert Connelly Dam 3 serves the following purposes: Irrigation, Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Robert Connelly Dam 3?
Robert Connelly Dam 3 has a dam height of 14 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Robert Connelly Dam 3 last inspected?
Robert Connelly Dam 3 was last inspected on August 23, 2017. Inspection dates indicate when a formal review occurred, not the results of that inspection.