Rifle Valley
Key Takeaway
Rifle Valley is classified as low hazard in Colorado. It was completed in 1906 and is 120 years old. Its primary use is fish and wildlife pond.
Physical Details
| Dam Height | 20 ft (taller than 36.1% in CO) |
| Dam Length | 240 ft |
| Dam Type | Earth |
| Max Storage | 680 acre-ft |
| Normal Storage | 3 acre-ft |
| Surface Area | 1 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 42 cfs |
| Year Completed | 1906 (120 years old) |
| NID ID | CO00697 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
U.S. BUREAU OF LAND MANAGEMENT
Federal Government
Nearby Dams
Frequently Asked Questions
What is the hazard classification of Rifle Valley?
Rifle Valley is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Rifle Valley?
Rifle Valley is owned by U.S. BUREAU OF LAND MANAGEMENT (Federal Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Rifle Valley built?
Rifle Valley was completed in 1906, making it 120 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Rifle Valley?
Rifle Valley serves the following purposes: Fish And Wildlife Pond. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Rifle Valley?
Rifle Valley has a dam height of 20 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Rifle Valley last inspected?
Rifle Valley was last inspected on June 13, 1989. Inspection dates indicate when a formal review occurred, not the results of that inspection.