Reelfootindian Creek #4
Key Takeaway
Reelfootindian Creek #4 is classified as significant hazard in Tennessee. It was completed in 1990 and is 36 years old. Its primary use is flood risk reduction. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Length | 1,986 ft |
| Dam Type | Earth |
| Max Storage | 4.3K acre-ft |
| Normal Storage | 722 acre-ft |
| Surface Area | 107 acres |
| Drainage Area | 6 sq mi |
| Year Completed | 1990 (36 years old) |
| NID ID | TN13106 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
TWRA
State Government
Nearby Dams
Reelfootindian Creek #3
Obion, TN
Significant HazardReelfootindian Creek #2
Obion, TN
Significant HazardReelfootindian Creek #5
Obion, TN
Significant HazardEnglewood Lake
Obion, TN
Low HazardReelfootindian Creek #1
Obion, TN
High HazardReelfootindian Creek #7
Obion, TN
Low HazardReelfootindian Creek #14
Obion, TN
Low HazardReelfootindian Creek #15
Obion, TN
Significant HazardFrequently Asked Questions
What is the hazard classification of Reelfootindian Creek #4?
Reelfootindian Creek #4 is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Reelfootindian Creek #4?
Reelfootindian Creek #4 is owned by TWRA (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Reelfootindian Creek #4 built?
Reelfootindian Creek #4 was completed in 1990, making it 36 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Reelfootindian Creek #4?
Reelfootindian Creek #4 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Reelfootindian Creek #4 last inspected?
Reelfootindian Creek #4 was last inspected on October 10, 2019. Inspection dates indicate when a formal review occurred, not the results of that inspection.