Redmond Ridge East Srs 1 Pond No 1

Offstream - Snoqualmie R.· King, Washington· Built 2013· Earth·
High Hazard Flood Risk Reduction Local Government

Key Takeaway

Redmond Ridge East Srs 1 Pond No 1 is classified as high hazard in Washington. It was completed in 2013 and is 13 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.

Physical Details

Dam Length1,820 ft
Dam TypeEarth
Max Storage47 acre-ft
Normal Storage26 acre-ft
Drainage Area0 sq mi
Max Discharge284 cfs
Year Completed2013 (13 years old)
Year Modified2009
NID IDWA01922

Safety Information

High Hazard

Loss of human life is likely if the dam fails.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: Yes
Last Inspection: August 2, 2023
State Regulated: Yes
Regulatory Agency: Washington Dept of Ecology

Ownership

King County Natural Resources and Parks

Local Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Redmond Ridge East Srs 1 Pond No 1?

Redmond Ridge East Srs 1 Pond No 1 is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Redmond Ridge East Srs 1 Pond No 1?

Redmond Ridge East Srs 1 Pond No 1 is owned by King County Natural Resources and Parks (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Redmond Ridge East Srs 1 Pond No 1 built?

Redmond Ridge East Srs 1 Pond No 1 was completed in 2013, making it 13 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Redmond Ridge East Srs 1 Pond No 1?

Redmond Ridge East Srs 1 Pond No 1 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

When was Redmond Ridge East Srs 1 Pond No 1 last inspected?

Redmond Ridge East Srs 1 Pond No 1 was last inspected on August 2, 2023. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.