Redmond Ridge East Srs 1 Pond No 1
Key Takeaway
Redmond Ridge East Srs 1 Pond No 1 is classified as high hazard in Washington. It was completed in 2013 and is 13 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Length | 1,820 ft |
| Dam Type | Earth |
| Max Storage | 47 acre-ft |
| Normal Storage | 26 acre-ft |
| Drainage Area | 0 sq mi |
| Max Discharge | 284 cfs |
| Year Completed | 2013 (13 years old) |
| Year Modified | 2009 |
| NID ID | WA01922 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
King County Natural Resources and Parks
Local Government
Nearby Dams
Redmond Ridge East Pond Srn 2 No 1
King, WA
High HazardRedmond Ridge Drive Ec 4n Roadway Dam
King, WA
High HazardPeterson Stormwater Detention Dam
King, WA
High HazardRedmond Ridge Cedar Dam
King, WA
High HazardLoutsis Dam
King, WA
Low HazardJohnson Pond Dam
King, WA
High HazardRadar Lake Dam
King, WA
High HazardWelcome Lake Dam
King, WA
High HazardFrequently Asked Questions
What is the hazard classification of Redmond Ridge East Srs 1 Pond No 1?
Redmond Ridge East Srs 1 Pond No 1 is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Redmond Ridge East Srs 1 Pond No 1?
Redmond Ridge East Srs 1 Pond No 1 is owned by King County Natural Resources and Parks (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Redmond Ridge East Srs 1 Pond No 1 built?
Redmond Ridge East Srs 1 Pond No 1 was completed in 2013, making it 13 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Redmond Ridge East Srs 1 Pond No 1?
Redmond Ridge East Srs 1 Pond No 1 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Redmond Ridge East Srs 1 Pond No 1 last inspected?
Redmond Ridge East Srs 1 Pond No 1 was last inspected on August 2, 2023. Inspection dates indicate when a formal review occurred, not the results of that inspection.