Redmond Ridge Drive Ec 4n Roadway Dam
Key Takeaway
Redmond Ridge Drive Ec 4n Roadway Dam is classified as high hazard in Washington. It was completed in 2003 and is 23 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Length | 800 ft |
| Dam Type | Earth |
| Max Storage | 148 acre-ft |
| Normal Storage | 1 acre-ft |
| Surface Area | 8 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 62 cfs |
| Year Completed | 2003 (23 years old) |
| NID ID | WA01837 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
King County Natural Resources and Parks
Local Government
Nearby Dams
Peterson Stormwater Detention Dam
King, WA
High HazardRedmond Ridge East Srs 1 Pond No 1
King, WA
High HazardRedmond Ridge East Pond Srn 2 No 1
King, WA
High HazardRedmond Ridge Cedar Dam
King, WA
High HazardJohnson Pond Dam
King, WA
High HazardWelcome Lake Dam
King, WA
High HazardRadar Lake Dam
King, WA
High HazardLoutsis Dam
King, WA
Low HazardFrequently Asked Questions
What is the hazard classification of Redmond Ridge Drive Ec 4n Roadway Dam?
Redmond Ridge Drive Ec 4n Roadway Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Redmond Ridge Drive Ec 4n Roadway Dam?
Redmond Ridge Drive Ec 4n Roadway Dam is owned by King County Natural Resources and Parks (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Redmond Ridge Drive Ec 4n Roadway Dam built?
Redmond Ridge Drive Ec 4n Roadway Dam was completed in 2003, making it 23 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Redmond Ridge Drive Ec 4n Roadway Dam?
Redmond Ridge Drive Ec 4n Roadway Dam serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Redmond Ridge Drive Ec 4n Roadway Dam last inspected?
Redmond Ridge Drive Ec 4n Roadway Dam was last inspected on July 13, 2023. Inspection dates indicate when a formal review occurred, not the results of that inspection.