Plymouth Reservoir Dam is classified as significant hazard in New York. It was completed in 1827 and is 199 years old. Its primary use is recreation. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 12 ft (taller than 23.2% in NY) |
| Dam Length | 150 ft |
| Dam Type | Rockfill |
| Max Storage | 400 acre-ft |
| Normal Storage | 320 acre-ft |
| Surface Area | 77 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 16 cfs |
| Year Completed | 1827 (199 years old) |
| NID ID | NY01481 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
PLYMOUTH RESERVOIR ASSOCIATION
Private
Nearby Dams
Norwich Ymca Recreation Pond Dam
Chenango, NY
Significant Hazard 39 ftSteer Pond Dam
Chenango, NY
Low Hazard 14 ftLake Lorraine Dam
Chenango, NY
Low Hazard 20 ftChenango 1 Wildlife Marsh Dam
Chenango, NY
Low Hazard 9 ftBowman Creek Dam
Chenango, NY
Low Hazard 20 ftTriah Lake Dam
Chenango, NY
Low Hazard 23 ftJackson Pond Dam
Chenango, NY
Significant Hazard 15 ftLouis Dunckel Dam
Chenango, NY
Low Hazard 21 ftFrequently Asked Questions
What is the hazard classification of Plymouth Reservoir Dam?
Plymouth Reservoir Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Plymouth Reservoir Dam?
Plymouth Reservoir Dam is owned by PLYMOUTH RESERVOIR ASSOCIATION (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Plymouth Reservoir Dam built?
Plymouth Reservoir Dam was completed in 1827, making it 199 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Plymouth Reservoir Dam?
Plymouth Reservoir Dam serves the following purposes: Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Plymouth Reservoir Dam?
Plymouth Reservoir Dam has a dam height of 12 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Plymouth Reservoir Dam last inspected?
Plymouth Reservoir Dam was last inspected on May 15, 2019. Inspection dates indicate when a formal review occurred, not the results of that inspection.