Lucian Hill Dam
Key Takeaway
Lucian Hill Dam is classified as significant hazard in New York. It was completed in 1967 and is 59 years old. Its primary use is fire protection. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 16 ft (taller than 42.9% in NY) |
| Dam Length | 750 ft |
| Dam Type | Earth |
| Max Storage | 18 acre-ft |
| Normal Storage | 13 acre-ft |
| Surface Area | 5 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 27 cfs |
| Year Completed | 1967 (59 years old) |
| NID ID | NY10946 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Diane Reimels
Private
Nearby Dams
Wayland Reservoir Dam
Steuben, NY
Low Hazard 16 ftDansville Reservoir Dam
Steuben, NY
High Hazard 54 ftBeachville Dam
Steuben, NY
Low Hazard 8 ftVillage of Naples Dam
Ontario, NY
Low Hazard 25 ftLake Wellington Dam - Camp Cutler
Ontario, NY
Significant Hazard 35 ftConesus Inlet W M A Dam
Livingston, NY
Low Hazard 11 ftBradner Creek Dam
Livingston, NY
Low Hazard 34 ftOntario Parks Dam
Ontario, NY
High Hazard 20 ftFrequently Asked Questions
What is the hazard classification of Lucian Hill Dam?
Lucian Hill Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Lucian Hill Dam?
Lucian Hill Dam is owned by Diane Reimels (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Lucian Hill Dam built?
Lucian Hill Dam was completed in 1967, making it 59 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Lucian Hill Dam?
Lucian Hill Dam serves the following purposes: Fire Protection, Stock, Or Small Fish Pond. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Lucian Hill Dam?
Lucian Hill Dam has a dam height of 16 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Lucian Hill Dam last inspected?
Lucian Hill Dam was last inspected on November 8, 2017. Inspection dates indicate when a formal review occurred, not the results of that inspection.