Lloyd Sutton Dam
Key Takeaway
Lloyd Sutton Dam is classified as significant hazard in New York. It was completed in 1968 and is 58 years old. Its primary use is fire protection. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 12 ft (taller than 23.2% in NY) |
| Dam Length | 1,590 ft |
| Dam Type | Earth |
| Max Storage | 50 acre-ft |
| Normal Storage | 41 acre-ft |
| Surface Area | 8 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 132 cfs |
| Year Completed | 1968 (58 years old) |
| NID ID | NY01052 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
LLOYD SUTTON
Private
Nearby Dams
Ben Bradley Wildlife Dam & Dike
Cortland, NY
Low Hazard 11 ftSolon Pond Dam
Cortland, NY
Low Hazard 12 ftKnapp Pond Dam
Chenango, NY
Low Hazard 10 ftOtis Young Dam
Cortland, NY
Low Hazard 14 ftTully Forest Pond #1 Dam
Cortland, NY
Significant Hazard 9 ftBelnap Briggs & Stremba Pond Dam
Cortland, NY
Low Hazard 9 ftElmcrest Childrens Center Dam
Onondaga, NY
Low Hazard 23 ftDeruyter Dam
Onondaga, NY
High Hazard 68 ftFrequently Asked Questions
What is the hazard classification of Lloyd Sutton Dam?
Lloyd Sutton Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Lloyd Sutton Dam?
Lloyd Sutton Dam is owned by LLOYD SUTTON (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Lloyd Sutton Dam built?
Lloyd Sutton Dam was completed in 1968, making it 58 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Lloyd Sutton Dam?
Lloyd Sutton Dam serves the following purposes: Fire Protection, Stock, Or Small Fish Pond, Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Lloyd Sutton Dam?
Lloyd Sutton Dam has a dam height of 12 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Lloyd Sutton Dam last inspected?
Lloyd Sutton Dam was last inspected on October 16, 2018. Inspection dates indicate when a formal review occurred, not the results of that inspection.