Lithco Mine Tailings Dam F
Key Takeaway
Lithco Mine Tailings Dam F is classified as high hazard in North Carolina. It was completed in 1992 and is 34 years old. Its primary use is other. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Length | 792 ft |
| Dam Type | Earth |
| Max Storage | 56 acre-ft |
| Normal Storage | 0 acre-ft |
| Surface Area | 4 acres |
| Drainage Area | 354 sq mi |
| Max Discharge | 0 cfs |
| Year Completed | 1992 (34 years old) |
| NID ID | NC02641 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Martin Marietta Materials, Inc.
Private
Nearby Dams
Lithium Lagoon D Dam
Gaston, NC
Significant HazardLithium Lagoon B Dam
Gaston, NC
Significant HazardLithium Lagoon A Dam
Gaston, NC
Significant HazardMartin-Marietta Quarry Dam
Gaston, NC
Significant HazardS.C. Lovelace Dam
Gaston, NC
Significant HazardArrowood Lake Dam
Gaston, NC
High HazardBen Webber Lake Dam
Gaston, NC
High HazardBessemer City Water Treatment Reservoir Dam
Gaston, NC
High HazardFrequently Asked Questions
What is the hazard classification of Lithco Mine Tailings Dam F?
Lithco Mine Tailings Dam F is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Lithco Mine Tailings Dam F?
Lithco Mine Tailings Dam F is owned by Martin Marietta Materials, Inc. (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Lithco Mine Tailings Dam F built?
Lithco Mine Tailings Dam F was completed in 1992, making it 34 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Lithco Mine Tailings Dam F?
Lithco Mine Tailings Dam F serves the following purposes: Other, Water Supply. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Lithco Mine Tailings Dam F last inspected?
Lithco Mine Tailings Dam F was last inspected on January 5, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.