Lander Wastewater Treatment
Key Takeaway
Lander Wastewater Treatment is classified as low hazard in Wyoming. It was completed in 1994 and is 32 years old. Its primary use is other.
Physical Details
| Dam Height | 14 ft (taller than 8.9% in WY) |
| Dam Length | 2,800 ft |
| Dam Type | Earth |
| Max Storage | 205 acre-ft |
| Normal Storage | 161 acre-ft |
| Surface Area | 15 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 0 cfs |
| Year Completed | 1994 (32 years old) |
| NID ID | WY02230 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
CITY OF LANDER
Local Government
Nearby Dams
Frequently Asked Questions
What is the hazard classification of Lander Wastewater Treatment?
Lander Wastewater Treatment is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Lander Wastewater Treatment?
Lander Wastewater Treatment is owned by CITY OF LANDER (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Lander Wastewater Treatment built?
Lander Wastewater Treatment was completed in 1994, making it 32 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Lander Wastewater Treatment?
Lander Wastewater Treatment serves the following purposes: Other. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Lander Wastewater Treatment?
Lander Wastewater Treatment has a dam height of 14 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Lander Wastewater Treatment last inspected?
Lander Wastewater Treatment was last inspected on July 25, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.