High Dam

Oswego River· Oswego, New York· Built 1928· Gravity· 35 ft tall
High Hazard Hydroelectric Navigation State Government

Key Takeaway

High Dam is classified as high hazard in New York. It was completed in 1928 and is 98 years old. Its primary use is hydroelectric. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.

Physical Details

Dam Height 35 ft (taller than 83.6% in NY)
Dam Length900 ft
Dam TypeGravity
Max Storage3.9K acre-ft
Normal Storage3.9K acre-ft
Surface Area240 acres
Drainage Area5,097 sq mi
Max Discharge32,500 cfs
Year Completed1928 (98 years old)
NID IDNY00401

Safety Information

High Hazard

Loss of human life is likely if the dam fails.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: Yes
Last Inspection: August 9, 2022
State Regulated: No

Ownership

New York State Canal Corporation

State Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of High Dam?

High Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates High Dam?

High Dam is owned by New York State Canal Corporation (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was High Dam built?

High Dam was completed in 1928, making it 98 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of High Dam?

High Dam serves the following purposes: Hydroelectric, Navigation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is High Dam?

High Dam has a dam height of 35 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was High Dam last inspected?

High Dam was last inspected on August 9, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.