Elgin Mill Trmt. Lagoon #2
Key Takeaway
Elgin Mill Trmt. Lagoon #2 is classified as significant hazard in Oregon. It was completed in 2017 and is 9 years old. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 36 ft (taller than 72.6% in OR) |
| Dam Type | Earth |
| Normal Storage | 82 acre-ft |
| Year Completed | 2017 (9 years old) |
| NID ID | OR04072 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
BOISE CASCADE WOOD PRODUCTS
Private
Nearby Dams
Frequently Asked Questions
What is the hazard classification of Elgin Mill Trmt. Lagoon #2?
Elgin Mill Trmt. Lagoon #2 is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Elgin Mill Trmt. Lagoon #2?
Elgin Mill Trmt. Lagoon #2 is owned by BOISE CASCADE WOOD PRODUCTS (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Elgin Mill Trmt. Lagoon #2 built?
Elgin Mill Trmt. Lagoon #2 was completed in 2017, making it 9 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
How tall is Elgin Mill Trmt. Lagoon #2?
Elgin Mill Trmt. Lagoon #2 has a dam height of 36 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Elgin Mill Trmt. Lagoon #2 last inspected?
Elgin Mill Trmt. Lagoon #2 was last inspected on September 5, 2018. Inspection dates indicate when a formal review occurred, not the results of that inspection.