Domain Subdivision Pond A

TRIBUTARY SLOAN CREEK· Collin, Texas· Built 2003· Earth· 18 ft tall
Significant Hazard Private

Key Takeaway

Domain Subdivision Pond A is classified as significant hazard in Texas. It was completed in 2003 and is 23 years old. Significant hazard means failure could cause economic or environmental damage. Learn more.

Physical Details

Dam Height 18 ft (taller than 25.8% in TX)
Dam Length280 ft
Dam TypeEarth
Max Storage13 acre-ft
Normal Storage5 acre-ft
Surface Area1 acres
Drainage Area0 sq mi
Max Discharge595 cfs
Year Completed2003 (23 years old)
NID IDTX09718

Safety Information

Significant Hazard

No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: June 2, 2022
State Regulated: Yes
Regulatory Agency: TCEQ

Ownership

WILBOW-FAIRVIEW NO 1 DEVELOPMENT CORPORATION

Private

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Domain Subdivision Pond A?

Domain Subdivision Pond A is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Domain Subdivision Pond A?

Domain Subdivision Pond A is owned by WILBOW-FAIRVIEW NO 1 DEVELOPMENT CORPORATION (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Domain Subdivision Pond A built?

Domain Subdivision Pond A was completed in 2003, making it 23 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

How tall is Domain Subdivision Pond A?

Domain Subdivision Pond A has a dam height of 18 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Domain Subdivision Pond A last inspected?

Domain Subdivision Pond A was last inspected on June 2, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.