Dd No 6-1
Key Takeaway
Dd No 6-1 is classified as low hazard in Kansas. Its primary use is flood risk reduction.
Physical Details
| Dam Height | 25 ft (taller than 46.5% in KS) |
| Dam Length | 890 ft |
| Dam Type | Earth |
| Max Storage | 184 acre-ft |
| Normal Storage | 34 acre-ft |
| Surface Area | 8 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 1,460 cfs |
| NID ID | KS09181 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
TAUY CREEK WJD NO 82
Local Government
Nearby Dams
Dd No 7-1 (Jammison)
Douglas, KS
Low Hazard 22 ftDd No 7-12
Douglas, KS
Low Hazard 22 ftDd No 7-35
Douglas, KS
Low Hazard 26 ftDam KS00572
Douglas, KS
Low Hazard 22 ftDd No 7-26
Douglas, KS
High Hazard 40 ftDam KS00029
Douglas, KS
Low Hazard 22 ftDd No 7-30
Douglas, KS
Low Hazard 23 ftDam KS04080
Douglas, KS
Low Hazard 24 ftFrequently Asked Questions
What is the hazard classification of Dd No 6-1?
Dd No 6-1 is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Dd No 6-1?
Dd No 6-1 is owned by TAUY CREEK WJD NO 82 (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
What is the primary purpose of Dd No 6-1?
Dd No 6-1 serves the following purposes: Flood Risk Reduction, Debris Control. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Dd No 6-1?
Dd No 6-1 has a dam height of 25 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Dd No 6-1 last inspected?
Dd No 6-1 was last inspected on August 22, 1997. Inspection dates indicate when a formal review occurred, not the results of that inspection.