Dd No 116
Key Takeaway
Dd No 116 is classified as low hazard in Kansas. Its primary use is flood risk reduction.
Physical Details
| Dam Height | 38 ft (taller than 90.5% in KS) |
| Dam Length | 750 ft |
| Dam Type | Earth |
| Max Storage | 331 acre-ft |
| Normal Storage | 38 acre-ft |
| Surface Area | 6 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 903 cfs |
| NID ID | KS09210 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
CROSS CREEK WJD NO 42
Local Government
Nearby Dams
Frd No 6
Pottawatomie, KS
High Hazard 40 ftDam KS04509
Pottawatomie, KS
Low Hazard 29 ftFrd No 7
Pottawatomie, KS
Significant Hazard 36 ftDam KS04505
Pottawatomie, KS
Low Hazard 30 ftDam KS01748
Pottawatomie, KS
Low Hazard 28 ftFrd No 8
Pottawatomie, KS
Low Hazard 48 ftDam KS04519
Pottawatomie, KS
Low Hazard 28 ftDam KS04504
Pottawatomie, KS
Low Hazard 17 ftFrequently Asked Questions
What is the hazard classification of Dd No 116?
Dd No 116 is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Dd No 116?
Dd No 116 is owned by CROSS CREEK WJD NO 42 (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
What is the primary purpose of Dd No 116?
Dd No 116 serves the following purposes: Flood Risk Reduction, Debris Control. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Dd No 116?
Dd No 116 has a dam height of 38 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Dd No 116 last inspected?
Dd No 116 was last inspected on March 15, 1996. Inspection dates indicate when a formal review occurred, not the results of that inspection.