Dam No 1
Key Takeaway
Dam No 1 is classified as high hazard in Kansas. Its primary use is recreation. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 65 ft (taller than 99.2% in KS) |
| Dam Length | 1,425 ft |
| Dam Type | Earth |
| Max Storage | 2.7K acre-ft |
| Normal Storage | 1.6K acre-ft |
| Surface Area | 84 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 4,137 cfs |
| NID ID | KS04637 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
SUGAR VALLEY LAKE HOMES ASSOCIATION, INC.
Private
Nearby Dams
Dam No 2
Linn, KS
High Hazard 57 ftDam No 5
Linn, KS
Significant Hazard 22 ftDam No 3
Linn, KS
High Hazard 38 ftDam No 4
Linn, KS
High Hazard 32 ftDam KS01291
Linn, KS
Low Hazard 30 ftDam KS04398
Linn, KS
Low Hazard 28 ftDam KS05030
Linn, KS
Low Hazard 22 ftDam KS07344
Linn, KS
Low Hazard 12 ftFrequently Asked Questions
What is the hazard classification of Dam No 1?
Dam No 1 is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Dam No 1?
Dam No 1 is owned by SUGAR VALLEY LAKE HOMES ASSOCIATION, INC. (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
What is the primary purpose of Dam No 1?
Dam No 1 serves the following purposes: Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Dam No 1?
Dam No 1 has a dam height of 65 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Dam No 1 last inspected?
Dam No 1 was last inspected on July 15, 2021. Inspection dates indicate when a formal review occurred, not the results of that inspection.