Cook Southeast Dam
Key Takeaway
Cook Southeast Dam is classified as low hazard in Nebraska. It was completed in 1953 and is 73 years old. Its primary use is fire protection.
Physical Details
| Dam Height | 7 ft |
| Dam Length | 455 ft |
| Dam Type | Earth |
| Max Storage | 123 acre-ft |
| Normal Storage | 65 acre-ft |
| Surface Area | 28 acres |
| Drainage Area | 188 sq mi |
| Max Discharge | 902 cfs |
| Year Completed | 1953 (73 years old) |
| NID ID | NE01242 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Schiff Farms Inc
Private
Nearby Dams
Frequently Asked Questions
What is the hazard classification of Cook Southeast Dam?
Cook Southeast Dam is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Cook Southeast Dam?
Cook Southeast Dam is owned by Schiff Farms Inc (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Cook Southeast Dam built?
Cook Southeast Dam was completed in 1953, making it 73 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Cook Southeast Dam?
Cook Southeast Dam serves the following purposes: Fire Protection, Stock, Or Small Fish Pond. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Cook Southeast Dam?
Cook Southeast Dam has a dam height of 7 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Cook Southeast Dam last inspected?
Cook Southeast Dam was last inspected on April 21, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.