Clinch Belser Dam

TR-BIG CEDAR CREEK· Fairfield, South Carolina· Built 1994· 35 ft tall
Low Hazard Fish And Wildlife Pond Recreation Private

Key Takeaway

Clinch Belser Dam is classified as low hazard in South Carolina. It was completed in 1994 and is 32 years old. Its primary use is fish and wildlife pond.

Physical Details

Dam Height 35 ft (taller than 87.9% in SC)
Max Storage250 acre-ft
Normal Storage141 acre-ft
Surface Area19 acres
Year Completed1994 (32 years old)
NID IDSC02670

Safety Information

Low Hazard

No probable loss of human life and low economic/environmental losses expected.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: April 27, 2017
State Regulated: Yes
Regulatory Agency: SC DHEC

Ownership

FAIRVIEW FARMING COMPANY

Private

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Clinch Belser Dam?

Clinch Belser Dam is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Clinch Belser Dam?

Clinch Belser Dam is owned by FAIRVIEW FARMING COMPANY (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Clinch Belser Dam built?

Clinch Belser Dam was completed in 1994, making it 32 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Clinch Belser Dam?

Clinch Belser Dam serves the following purposes: Fish And Wildlife Pond, Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Clinch Belser Dam?

Clinch Belser Dam has a dam height of 35 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Clinch Belser Dam last inspected?

Clinch Belser Dam was last inspected on April 27, 2017. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.