Bumphead Reservoir

LOST RIVER, TRIB TO· Klamath, Oregon· Built 1957· Earth· 25 ft tall
Low Hazard Irrigation Local Government

Key Takeaway

Bumphead Reservoir is classified as low hazard in Oregon. It was completed in 1957 and is 69 years old. Its primary use is irrigation.

Physical Details

Dam Height 25 ft (taller than 43.9% in OR)
Dam Length500 ft
Dam TypeEarth
Max Storage1.5K acre-ft
Normal Storage1.5K acre-ft
Surface Area125 acres
Drainage Area4 sq mi
Max Discharge988 cfs
Year Completed1957 (69 years old)
NID IDOR00330

Safety Information

Low Hazard

No probable loss of human life and low economic/environmental losses expected.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: August 12, 2015
State Regulated: Yes
Regulatory Agency: OWRD

Ownership

WILLOW VALLEY RANCH, C/O DARREL BAGLEY

Local Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Bumphead Reservoir?

Bumphead Reservoir is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Bumphead Reservoir?

Bumphead Reservoir is owned by WILLOW VALLEY RANCH, C/O DARREL BAGLEY (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Bumphead Reservoir built?

Bumphead Reservoir was completed in 1957, making it 69 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Bumphead Reservoir?

Bumphead Reservoir serves the following purposes: Irrigation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Bumphead Reservoir?

Bumphead Reservoir has a dam height of 25 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Bumphead Reservoir last inspected?

Bumphead Reservoir was last inspected on August 12, 2015. Inspection dates indicate when a formal review occurred, not the results of that inspection.