Big Sandy Creek WS SCS Site 26 Dam
Key Takeaway
Big Sandy Creek WS SCS Site 26 Dam is classified as high hazard in Texas. It was completed in 1984 and is 42 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 23 ft (taller than 44.9% in TX) |
| Dam Length | 1,630 ft |
| Dam Type | Earth |
| Max Storage | 402 acre-ft |
| Normal Storage | 129 acre-ft |
| Surface Area | 18 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 662 cfs |
| Year Completed | 1984 (42 years old) |
| NID ID | TX06844 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
TARRANT REGIONAL WATER DISTRICT;WISE COUNTY;WISE COUNTY WCID;WISE SWCD
State Government
Nearby Dams
Big Sandy Creek WS SCS Gss 122
Wise, TX
Low Hazard 27 ftBig Sandy Creek WS SCS Site 24d Dam
Wise, TX
High Hazard 38 ftBig Sandy Creek WS SCS Site 27 Dam
Wise, TX
Low Hazard 30 ftBig Sandy Creek WS NRCS Site 24c Dam
Wise, TX
Low Hazard 45 ftBig Sandy Creek WS SCS Gss 118
Wise, TX
Low Hazard 32 ftBig Sandy Creek WS SCS Site 24a Dam
Wise, TX
Low Hazard 44 ftBig Sandy Creek WS SCS Site 24b Dam
Wise, TX
High Hazard 33 ftBig Sandy Creek WS SCS Gss 125a
Wise, TX
Low Hazard 36 ftFrequently Asked Questions
What is the hazard classification of Big Sandy Creek WS SCS Site 26 Dam?
Big Sandy Creek WS SCS Site 26 Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Big Sandy Creek WS SCS Site 26 Dam?
Big Sandy Creek WS SCS Site 26 Dam is owned by TARRANT REGIONAL WATER DISTRICT;WISE COUNTY;WISE COUNTY WCID;WISE SWCD (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Big Sandy Creek WS SCS Site 26 Dam built?
Big Sandy Creek WS SCS Site 26 Dam was completed in 1984, making it 42 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Big Sandy Creek WS SCS Site 26 Dam?
Big Sandy Creek WS SCS Site 26 Dam serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Big Sandy Creek WS SCS Site 26 Dam?
Big Sandy Creek WS SCS Site 26 Dam has a dam height of 23 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Big Sandy Creek WS SCS Site 26 Dam last inspected?
Big Sandy Creek WS SCS Site 26 Dam was last inspected on November 23, 2021. Inspection dates indicate when a formal review occurred, not the results of that inspection.