W1 Phase2 South Pasture is classified as significant hazard in Florida. It was completed in 2003 and is 23 years old. Its primary use is tailings. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 35 ft (taller than 75.5% in FL) |
| Dam Length | 11,680 ft |
| Dam Type | Earth |
| Max Storage | 14.0K acre-ft |
| Normal Storage | 12.6K acre-ft |
| Surface Area | 420 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 20 cfs |
| Year Completed | 2003 (23 years old) |
| NID ID | FL11076 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
THE MOSAIC COMPANY
Private
Nearby Dams
Har5
Hardee, FL
Unknown 16 ftW2 Mix Area South Pasture
Hardee, FL
Significant Hazard 30 ftHar6
Hardee, FL
Unknown 16 ftSouth Pasture Isa
Hardee, FL
Significant Hazard 45 ftE3 Mix Area South Pasture
Hardee, FL
Significant Hazard 40 ftW1mix Area South Pasture
Hardee, FL
Significant Hazard 35 ftHar7
Hardee, FL
Unknown 23 ftHar4
Hardee, FL
Unknown 7 ftFrequently Asked Questions
What is the hazard classification of W1 Phase2 South Pasture?
W1 Phase2 South Pasture is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates W1 Phase2 South Pasture?
W1 Phase2 South Pasture is owned by THE MOSAIC COMPANY (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was W1 Phase2 South Pasture built?
W1 Phase2 South Pasture was completed in 2003, making it 23 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of W1 Phase2 South Pasture?
W1 Phase2 South Pasture serves the following purposes: Tailings. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is W1 Phase2 South Pasture?
W1 Phase2 South Pasture has a dam height of 35 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was W1 Phase2 South Pasture last inspected?
W1 Phase2 South Pasture was last inspected on January 23, 2006. Inspection dates indicate when a formal review occurred, not the results of that inspection.