Upriver Dam

Spokane River· Spokane, Washington· Built 1937· Concrete· 38 ft tall
High Hazard Hydroelectric Recreation Local Government

Key Takeaway

Upriver Dam is classified as high hazard in Washington. It was completed in 1937 and is 89 years old. Its primary use is hydroelectric. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.

Physical Details

Dam Height 38 ft (taller than 43.5% in WA)
Dam Length725 ft
Dam TypeConcrete
Normal Storage3.0K acre-ft
Surface Area50 acres
Drainage Area4,057 sq mi
Max Discharge58,000 cfs
Year Completed1937 (89 years old)
NID IDWA00074

Safety Information

High Hazard

Loss of human life is likely if the dam fails.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: Yes
Last Inspection: August 18, 2022
State Regulated: No

Ownership

City of Spokane

Local Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Upriver Dam?

Upriver Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Upriver Dam?

Upriver Dam is owned by City of Spokane (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Upriver Dam built?

Upriver Dam was completed in 1937, making it 89 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Upriver Dam?

Upriver Dam serves the following purposes: Hydroelectric, Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Upriver Dam?

Upriver Dam has a dam height of 38 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Upriver Dam last inspected?

Upriver Dam was last inspected on August 18, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.