Round Mountain Detention Dam 3
Key Takeaway
Round Mountain Detention Dam 3 is classified as low hazard in New Mexico. It was completed in 1956 and is 70 years old. Its primary use is flood risk reduction.
Physical Details
| Dam Length | 1,176 ft |
| Dam Type | Gravity |
| Max Storage | 167 acre-ft |
| Normal Storage | 460 acre-ft |
| Surface Area | 64 acres |
| Drainage Area | 36 sq mi |
| Max Discharge | 1,918 cfs |
| Year Completed | 1956 (70 years old) |
| NID ID | NM00119 |
Safety Information
No probable loss of human life and low economic/environmental losses expected.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
DOI BLM
Federal Government
Nearby Dams
Dagger Draw Detention Dam 1
Hidalgo, NM
Low HazardHorseshoe Terrace Detention Dam
Hidalgo, NM
Low HazardDagger Draw Detention Dam 2
Hidalgo, NM
Low HazardState Line Detention Dam
Greenlee, AZ
Low HazardGrayhorse Detention Dam
Greenlee, AZ
Low HazardStanford Detention Dam 1
Hidalgo, NM
Low HazardRound Mountain Detention Dam 2
Greenlee, AZ
Low HazardOlney Draw Detention Dam
Greenlee, AZ
Low HazardFrequently Asked Questions
What is the hazard classification of Round Mountain Detention Dam 3?
Round Mountain Detention Dam 3 is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Round Mountain Detention Dam 3?
Round Mountain Detention Dam 3 is owned by DOI BLM (Federal Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Round Mountain Detention Dam 3 built?
Round Mountain Detention Dam 3 was completed in 1956, making it 70 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Round Mountain Detention Dam 3?
Round Mountain Detention Dam 3 serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Round Mountain Detention Dam 3 last inspected?
Round Mountain Detention Dam 3 was last inspected on July 20, 2015. Inspection dates indicate when a formal review occurred, not the results of that inspection.