Key Takeaway
Rancho Haven #2 Dam is classified as significant hazard in Nevada. Its primary use is irrigation. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 12 ft (taller than 17.5% in NV) |
| Dam Length | 700 ft |
| Dam Type | Earth |
| Max Storage | 12 acre-ft |
| Normal Storage | 12 acre-ft |
| Surface Area | 5 acres |
| Drainage Area | 5 sq mi |
| Max Discharge | 10 cfs |
| Year Modified | 2015 |
| NID ID | NV10568 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
RANCHO HAVEN PROPERTY OWNER'S ASSOCIATION
Private
Nearby Dams
Frequently Asked Questions
What is the hazard classification of Rancho Haven #2 Dam?
Rancho Haven #2 Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Rancho Haven #2 Dam?
Rancho Haven #2 Dam is owned by RANCHO HAVEN PROPERTY OWNER'S ASSOCIATION (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
What is the primary purpose of Rancho Haven #2 Dam?
Rancho Haven #2 Dam serves the following purposes: Irrigation, Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Rancho Haven #2 Dam?
Rancho Haven #2 Dam has a dam height of 12 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Rancho Haven #2 Dam last inspected?
Rancho Haven #2 Dam was last inspected on June 15, 2023. Inspection dates indicate when a formal review occurred, not the results of that inspection.