Paulins Kill Site 4 Dam
Key Takeaway
Paulins Kill Site 4 Dam is classified as high hazard in New Jersey. It was completed in 1961 and is 65 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 24 ft (taller than 83.4% in NJ) |
| Dam Length | 400 ft |
| Dam Type | Earth |
| Max Storage | 10 acre-ft |
| Normal Storage | 10 acre-ft |
| Surface Area | 3 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 27 cfs |
| Year Completed | 1961 (65 years old) |
| NID ID | NJ00868 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Town of Newton
Local Government
Nearby Dams
Don Bosco Dam
Sussex, NJ
Low Hazard 25 ftPaulinskill Water Shed #2 Dam
Sussex, NJ
High Hazard 29 ftThomas Rich Dam
Sussex, NJ
Low Hazard 13 ftBalesville Dam
Sussex, NJ
Low Hazard 9 ftGlauberman Lake Dam
Sussex, NJ
Low Hazard 13 ftClearview Lake Dam
Sussex, NJ
Significant Hazard 10 ftKemah Lake Dam
Sussex, NJ
High Hazard 17 ftLake Aeroflex Dam
Sussex, NJ
Low Hazard 15 ftFrequently Asked Questions
What is the hazard classification of Paulins Kill Site 4 Dam?
Paulins Kill Site 4 Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Paulins Kill Site 4 Dam?
Paulins Kill Site 4 Dam is owned by Town of Newton (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Paulins Kill Site 4 Dam built?
Paulins Kill Site 4 Dam was completed in 1961, making it 65 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Paulins Kill Site 4 Dam?
Paulins Kill Site 4 Dam serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Paulins Kill Site 4 Dam?
Paulins Kill Site 4 Dam has a dam height of 24 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Paulins Kill Site 4 Dam last inspected?
Paulins Kill Site 4 Dam was last inspected on December 14, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.