Physical Details

Dam Height 29 ft (taller than 61.4% in NV)
Dam Length350 ft
Dam TypeEarth
Max Storage31 acre-ft
Normal Storage31 acre-ft
Surface Area2 acres
Drainage Area0 sq mi
Max Discharge50 cfs
NID IDNV10249

Safety Information

Low Hazard

No probable loss of human life and low economic/environmental losses expected.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: July 26, 2021
State Regulated: Yes
Regulatory Agency: NEVADA DWR

Ownership

NEVADA GOLD MINES LLC

Private

Nearby Dams

Frequently Asked Questions

What is the hazard classification of North Area Leachate Pond Addition Dam?

North Area Leachate Pond Addition Dam is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates North Area Leachate Pond Addition Dam?

North Area Leachate Pond Addition Dam is owned by NEVADA GOLD MINES LLC (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

What is the primary purpose of North Area Leachate Pond Addition Dam?

North Area Leachate Pond Addition Dam serves the following purposes: Other. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is North Area Leachate Pond Addition Dam?

North Area Leachate Pond Addition Dam has a dam height of 29 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was North Area Leachate Pond Addition Dam last inspected?

North Area Leachate Pond Addition Dam was last inspected on July 26, 2021. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.