Moose River Project

Moose River· Beltrami, Minnesota· Built 1986· Earth· 16 ft tall
Low Hazard Flood Risk Reduction Local Government

Key Takeaway

Moose River Project is classified as low hazard in Minnesota. It was completed in 1986 and is 40 years old. Its primary use is flood risk reduction.

Physical Details

Dam Height 16 ft (taller than 53.5% in MN)
Dam Length66,000 ft
Dam TypeEarth
Max Storage54.0K acre-ft
Normal Storage6.0K acre-ft
Surface Area3,500 acres
Drainage Area14 sq mi
Max Discharge500 cfs
Year Completed1986 (40 years old)
NID IDMN00929

Safety Information

Low Hazard

No probable loss of human life and low economic/environmental losses expected.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: June 11, 2015
State Regulated: Yes
Regulatory Agency: MNDNR EWR

Ownership

WD of Red Lake

Local Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Moose River Project?

Moose River Project is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Moose River Project?

Moose River Project is owned by WD of Red Lake (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Moose River Project built?

Moose River Project was completed in 1986, making it 40 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Moose River Project?

Moose River Project serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Moose River Project?

Moose River Project has a dam height of 16 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Moose River Project last inspected?

Moose River Project was last inspected on June 11, 2015. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.