Martin Marietta Maiden Quarry Dam
Key Takeaway
Martin Marietta Maiden Quarry Dam is classified as high hazard in North Carolina. It was completed in 1998 and is 28 years old. Its primary use is water supply. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Length | 600 ft |
| Dam Type | Earth |
| Max Storage | 81 acre-ft |
| Normal Storage | 69 acre-ft |
| Surface Area | 8 acres |
| Drainage Area | 290 sq mi |
| Year Completed | 1998 (28 years old) |
| Year Modified | 9999 |
| NID ID | NC05260 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Mark D Boyd
Private
Nearby Dams
Bel-Air Lake Dam
Catawba, NC
Low HazardKnolls Association Lake Dam
Catawba, NC
Low HazardReinhardt Pond Dam
Catawba, NC
Significant HazardGlen Oaks Golf Course Dam B
Lincoln, NC
High HazardJones Dam Lower
Lincoln, NC
Low HazardMaiden Water Plant Lake Dam
Catawba, NC
High HazardKaylor Pond Dam
Lincoln, NC
High HazardGladden Pond Dam
Lincoln, NC
High HazardFrequently Asked Questions
What is the hazard classification of Martin Marietta Maiden Quarry Dam?
Martin Marietta Maiden Quarry Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Martin Marietta Maiden Quarry Dam?
Martin Marietta Maiden Quarry Dam is owned by Mark D Boyd (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Martin Marietta Maiden Quarry Dam built?
Martin Marietta Maiden Quarry Dam was completed in 1998, making it 28 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Martin Marietta Maiden Quarry Dam?
Martin Marietta Maiden Quarry Dam serves the following purposes: Water Supply. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Martin Marietta Maiden Quarry Dam last inspected?
Martin Marietta Maiden Quarry Dam was last inspected on March 16, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.