Lakeside Development Dam
Key Takeaway
Lakeside Development Dam is classified as significant hazard in Iowa. It was completed in 2005 and is 21 years old. Its primary use is flood risk reduction. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 45 ft (taller than 91.4% in IA) |
| Dam Length | 385 ft |
| Dam Type | Earth |
| Max Storage | 237 acre-ft |
| Normal Storage | 127 acre-ft |
| Surface Area | 10 acres |
| Drainage Area | 1 sq mi |
| Max Discharge | 0 cfs |
| Year Completed | 2005 (21 years old) |
| NID ID | IA03515 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Lakeside Development LLC
Private
Nearby Dams
Cedar Rapids Milldam Iel&P
Linn, IA
Low Hazard 8 ftLehman Dam
Linn, IA
Low Hazard 18 ftCedar Rapids Milldam (5 In 1)
Linn, IA
Low Hazard 14 ftAegon Dam
Linn, IA
High Hazard 26 ftMorf Dam
Linn, IA
Low Hazard 33 ftPalisades-Kepler Dam
Linn, IA
Low Hazard 8 ftFenchel Dam
Linn, IA
Low Hazard 26 ftParsons Dam
Linn, IA
Low Hazard 29 ftFrequently Asked Questions
What is the hazard classification of Lakeside Development Dam?
Lakeside Development Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Lakeside Development Dam?
Lakeside Development Dam is owned by Lakeside Development LLC (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Lakeside Development Dam built?
Lakeside Development Dam was completed in 2005, making it 21 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Lakeside Development Dam?
Lakeside Development Dam serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Lakeside Development Dam?
Lakeside Development Dam has a dam height of 45 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Lakeside Development Dam last inspected?
Lakeside Development Dam was last inspected on July 19, 2017. Inspection dates indicate when a formal review occurred, not the results of that inspection.