La Luz-Fresnal East Reservoir
Key Takeaway
La Luz-Fresnal East Reservoir is classified as high hazard in New Mexico. It was completed in 1993 and is 33 years old. Its primary use is water supply. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Height | 37 ft (taller than 59.8% in NM) |
| Dam Length | 2,755 ft |
| Dam Type | Earth |
| Max Storage | 374 acre-ft |
| Normal Storage | 309 acre-ft |
| Surface Area | 14 acres |
| Max Discharge | 142 cfs |
| Year Completed | 1993 (33 years old) |
| NID ID | NM00572 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
CITY OF ALAMOGORDO
Local Government
Nearby Dams
Frequently Asked Questions
What is the hazard classification of La Luz-Fresnal East Reservoir?
La Luz-Fresnal East Reservoir is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates La Luz-Fresnal East Reservoir?
La Luz-Fresnal East Reservoir is owned by CITY OF ALAMOGORDO (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was La Luz-Fresnal East Reservoir built?
La Luz-Fresnal East Reservoir was completed in 1993, making it 33 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of La Luz-Fresnal East Reservoir?
La Luz-Fresnal East Reservoir serves the following purposes: Water Supply. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is La Luz-Fresnal East Reservoir?
La Luz-Fresnal East Reservoir has a dam height of 37 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was La Luz-Fresnal East Reservoir last inspected?
La Luz-Fresnal East Reservoir was last inspected on January 24, 2018. Inspection dates indicate when a formal review occurred, not the results of that inspection.