High Hill Pond Aka Shonek Pond Dam
Key Takeaway
High Hill Pond Aka Shonek Pond Dam is classified as significant hazard in Connecticut. It was completed in 1968 and is 58 years old. Its primary use is recreation. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 17 ft (taller than 66% in CT) |
| Dam Length | 230 ft |
| Dam Type | Earth |
| Normal Storage | 60 acre-ft |
| Surface Area | 12 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 90 cfs |
| Year Completed | 1968 (58 years old) |
| NID ID | CT01676 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Ronald E Shoneck Sr
Private
Nearby Dams
Bishops Pond Dam
New Haven, CT
Significant Hazard 13 ftBlack Pond Dam
New Haven, CT
High Hazard 26 ftPaddock Road Pond
New Haven, CT
Significant Hazard 8 ftBristol Myers Squibb Dam
New Haven, CT
Significant Hazard 12 ftLake Beseck Dam
Middlesex, CT
Significant Hazard 34 ftGunsight Pond Dam
Middlesex, CT
Significant Hazard 17 ftNorth Farms Reservoir Dam
New Haven, CT
Significant Hazard 5 ftSpring Lake Dam
New Haven, CT
Significant Hazard 9 ftFrequently Asked Questions
What is the hazard classification of High Hill Pond Aka Shonek Pond Dam?
High Hill Pond Aka Shonek Pond Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates High Hill Pond Aka Shonek Pond Dam?
High Hill Pond Aka Shonek Pond Dam is owned by Ronald E Shoneck Sr (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was High Hill Pond Aka Shonek Pond Dam built?
High Hill Pond Aka Shonek Pond Dam was completed in 1968, making it 58 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of High Hill Pond Aka Shonek Pond Dam?
High Hill Pond Aka Shonek Pond Dam serves the following purposes: Recreation. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is High Hill Pond Aka Shonek Pond Dam?
High Hill Pond Aka Shonek Pond Dam has a dam height of 17 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was High Hill Pond Aka Shonek Pond Dam last inspected?
High Hill Pond Aka Shonek Pond Dam was last inspected on August 7, 2015. Inspection dates indicate when a formal review occurred, not the results of that inspection.